POM Wonderful – ASHRAE Level 3 Energy Assessment

Featured Project

Imperion Identifies $720K in Annual Energy Cost Savings Opportunities for POM Wonderful Through Comprehensive Energy Assessment and M&V

Project Details

  • Business: Pom Wonderful
  • Category: Food & Beverage
  • Location: Del Ray, CA
  • Project Type: Energy Assessment | Measurement & Verification

Project Overview

POM Wonderful is a large-scale pomegranate processing and juice production facility. The facility operates year-round with energy-intensive washing, extraction, concentration, and bottling processes. Operations are highly seasonal, with production throughput and utility demand increasing significantly during the harvest season as fresh fruit is received, sorted, processed, and packaged. This fluctuating operating profile presents unique opportunities and challenges for optimizing energy performance while maintaining production reliability.

To reduce operating costs while advancing its internal sustainability goals, POM engaged Imperion to assess demand-side management (DSM) opportunities and identify California Energy Commission funding programs aligned with its capital improvement objectives. To position the facility for future funding opportunities, Imperion conducted a comprehensive Energy Efficiency Assessment to support the development of competitive grant applications for upcoming program solicitations.

The Energy Efficiency Assessment identified a broad portfolio of Energy Conservation Measures (ECMs) across multiple process and utility systems. To further quantify savings opportunities and validate system performance, Imperion also conducted detailed Measurement and Verification (M&V) activities on the facility’s refrigeration, compressed air, chilled water, and injection molding systems. By analyzing energy consumption, operating conditions, and system performance, Imperion updated the performance baselines, identified operational inefficiencies, and developed data-driven recommendations to support future capital improvements and competitive grant applications.

Detailed Electrical Demand and Power Quality Review

In parallel with the energy assessment and M&V effort, Imperion performed a detailed electrical demand and power quality review to evaluate capacity and reliability constraints affecting portions of the facility served by a targeted utility substation. The facility had experienced voltage drops that resulted in equipment failures and had been informed that the substation could not accommodate additional load growth, creating a potential constraint on future production expansion and electrification projects.

Imperion analyzed available 15-minute-interval data for both active and reactive power to characterize real power (kW), reactive power (kVAR), apparent power (kVA), and power factor across seasonal operating conditions. The analysis demonstrated that distributed energy resources, including onsite solar generation, can significantly reduce utility-supplied active power while leaving substantial reactive power requirements. As a result, transformers and upstream utility infrastructure may remain heavily loaded on a kVA basis even during periods when net facility kW demand appears relatively low.

The review identified peak apparent power requirements and provided additional insight into how reactive power demand contributes to existing electrical capacity constraints. Imperion also identified opportunities for additional equipment-level power monitoring and reactive power analysis to locate significant kVAR loads and evaluate potential corrective measures. Reducing these loads could help improve electrical infrastructure utilization, mitigate power quality concerns, and potentially create additional capacity for future production growth and electrification.

Through a comprehensive assessment and targeted M&V efforts, Imperion helped POM move beyond identifying energy-saving opportunities to develop a data-driven implementation roadmap. The analysis provided the technical foundation needed to prioritize projects, validate operational improvements, and pursue future funding opportunities to support long-term energy efficiency and cost-reduction goals.

Potential Energy Conservation Measures or Implemented Measures

  • Compressed Air System Retrofit
  • Refrigeration System Retrofit
  • Boiler System Retrofit
  • Hydraulic Power Units (HPUs) Retrofit
  • Lighting Retrofit
  • Advanced Motor Control Retrofit
  • Mechanical Vapor Recompression Retrofit
  • Chilled Water System Retrofit
  • Injection Molding Retrofit

Project Results

$719,954

Annual Electricity Cost Savings

205kWh

Peak Demand Savings

1,799,884 kWh

Annual Electric Savings

410 MTCO2e

Annual Carbon Footprint Reduction
  • Previous ProjectJessie Lord Bakery – RFSI Project

  • Next ProjectCentral Valley Meat

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.