RISE PA SAT Grant Development

Featured Project

Imperion Secures $499,234 RISE PA Grant for Industrial Refrigeration and Cooling Tunnel Modernization Project

Project Details

  • Business: Global Confectionery Manufacturer
  • Category: Food & Beverage
  • Location: Elizabethtown, PA
  • Project Type: Grant Application

Partners

  • Environmental Protection Agency (EPA)
  • Commonwealth of Pennsylvania

Project Overview

A leading global confectionery manufacturer operates its Elizabethtown, PA facility with the highest standards of quality, reliability, and food safety. The chocolate cooling tunnel at this facility plays a vital role in maintaining consistent product quality but relied on a legacy R-22 industrial refrigeration system, steam-driven desiccant dehumidification, and a complex multi-stage cooling process. Imperion secured critical funding through the RISE PA Small Scale Award Track (SAT) program to modernize this critical production asset, improving energy efficiency, reducing greenhouse gas (GHG) emissions, and enhancing long-term operational reliability.

Prior to the upgrade, the tunnel’s cooling system depended on a high-global warming potential (GWP) R-22 refrigeration system operating in conjunction with ethanol brine and desiccant cooling loops. This layered cooling architecture increased energy consumption, required steam for desiccant regeneration, and added unnecessary complexity to the facility’s central chilled water system. The project replaces this legacy configuration with a high-efficiency cooling tunnel served directly by the site’s existing chilled water system, eliminating the use of high-GWP refrigerants within the process while reducing electrical demand, steam consumption, and overall system complexity.

With Imperion’s successful procurement of RISE PA grant funding, the facility is now advancing a comprehensive modernization of its cooling process. The project replaces the outdated tunnel and associated infrastructure with a high-efficiency system integrated directly into the facility’s central chilled water system. This upgrade eliminates the use of R-22 refrigerant, ethanol brine, and liquid desiccant loops, and removes the parasitic energy burden associated with condenser heat rejection.

By simplifying the thermodynamic process and reducing layered energy usage, the new system is expected to significantly reduce GHG emissions, improve overall energy performance, and enhance long-term system reliability without impacting production capacity or product mix.

The project will be executed by the facility’s internal engineering team in partnership with qualified contractors. All work will comply with EPA refrigerant management standards, OSHA safety requirements, and FDA/FSMA food safety regulations. This investment underscores the manufacturer’s continued commitment to sustainability, operational excellence, and environmental responsibility.

Project Results

$499,234

RISE PA Grant Award

$3,906

Estimated Annual Energy Cost Savings

51,602 kWh

Estimated Annual Electricity Savings

3,380 lbs.

Estimated Annual R-22 Refrigerant Savings

2,790 MTCO2e

Estimated Annual GHG Emissions Savings
  • Previous ProjectRegional Medical Center

  • Next ProjectCrypto.com Arena

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.